Pasha Marjorie C – Full Installation BWTS

Bwts Full Installation

Avantis was awarded the installation of one Alfa Laval Pure Ballast 3.1 750m3/hr Ballast Water Treatment System (BWTS) and associated piping, electrical and instrumentation works.

Project Timescales / Delivery Time

  • Material Procurement: 3 – 4 Weeks
  • Prefabrication of galvanised spools and foundations: 3 – 4 Weeks
  • BWTS Mechanical & Electrical Installation: 3 Weeks
  • Avantis Offline Commissioning: 2 Days
  • Final Commissioning (BWTS OEM Team and Class Attendance): 2 Days
  • Timescales for procurement and prefabrication partially overlap.