Avantis was awarded the installation of one Alfa Laval Pure Ballast 3.1 750m3/hr Ballast Water Treatment System (BWTS) and associated piping, electrical and instrumentation works.
Project Timescales / Delivery Time
- Material Procurement: 3 – 4 Weeks
- Prefabrication of galvanised spools and foundations: 3 – 4 Weeks
- BWTS Mechanical & Electrical Installation: 3 Weeks
- Avantis Offline Commissioning: 2 Days
- Final Commissioning (BWTS OEM Team and Class Attendance): 2 Days
- Timescales for procurement and prefabrication partially overlap.